TG RERA orders refunds and penalties against eight developers

Hyderabad: The Telangana Real Estate Regulatory Authority (TG RERA) issued orders against eight real estate developers over violations involving project registration, construction delays, missing approvals and failure to deliver properties.

The TG RERA orders refunds with applicable interest in five cases, imposed a Rs 25 lakh penalty in another and directed the handover of a flat. The authority also ordered a developer to pay annual interest for delayed possession.

The orders addressed complaints involving financial losses, stalled construction, unregistered projects and disputes over property possession. TG RERA directed Sri Aditya Squares to refund Rs 17 lakh along with applicable interest.

In another case, the authority ordered Tripura Constructions to refund Rs 41.85 lakh with applicable interest. The developer had failed to secure the necessary approvals and begin construction.

Similarly, TG RERA directed SVM Aditya Homes to refund Rs 27.16 lakh with applicable interest. The company had failed to obtain Hyderabad Metropolitan Development Authority (HMDA) approvals and execute the project.

The authority also ordered BVR Infra Developers to refund Rs 7 lakh with applicable interest. The developer had failed to register the plot and hand over possession. In a separate case, TG RERA directed Bhuvanteza Infra Projects to refund Rs 26 lakh with applicable interest. The authority found that the developer had abandoned the project.

TG RERA orders refunds and imposes a penalty on an unregistered project

TG RERA imposed a Rs 25 lakh penalty on Sanali IT Parks over its unregistered SANALI THE EDGE project at Manchirevula. The authority also directed the company to stop advertising and selling units in the project until it secured the required registration.

Meanwhile, TG RERA ordered Vasavi Realtors to pay annual interest at 10.85% on Rs 49.50 lakh. The interest calculation began on February 7, 2025, and would continue until the developer handed over possession.

In another order, TG RERA directed Arine Infraa to immediately hand over Flat No. 502 in ARINE Emerald at Miyapur. The authority rejected the developer’s demand for an additional Rs 6.58 lakh after finding that the charges lacked supporting evidence.

The order required the developer to deliver possession without enforcing the unsupported additional payment demand. TG RERA warned the developers that failure to comply with its directions would attract further penalties under Section 63 of the Real Estate (Regulation and Development) Act.

The warning applied to the authority’s directions concerning refunds, interest payments, project registration restrictions and property handover.