Polavaram: Polavaram Project Authority (PPA) Chief Executive Officer Sanjeev Vohra said he is satisfied with the pace and quality of construction at the Polavaram irrigation project. He made the assessment during a day-long review on Tuesday. Vohra checked the progress of various components and inspected construction activities at the site. He also conducted on-the-spot quality tests.
Vohra was accompanied by PPA Member-Secretary M. Raghuram and Chief Engineer M. Ramesh Kumar. They reviewed progress at the project meeting hall with officials of the State Water Resources Department and representatives of Megha Engineering and Infrastructures Limited (MEIL). Officials and MEIL representatives gave a detailed PowerPoint presentation on the works. The CEO examined the status of various project components. He also sought updates on the suggestions and recommendations from his earlier visits and from the recent inspection by an international experts’ team.
Cyclonic activity hit the region last month, and fresh weather warnings are in place. Vohra therefore advised officials to take precautions against a possible rise in water levels. He told them to protect ongoing works from adverse weather. He also asked how many workers and machines are deployed to speed up construction.
Field inspection covers ECRF dam, G Hill and G Dash Hill
After the review meeting, Vohra toured the site with PPA and State Water Resources Department officials and MEIL representatives. The team inspected the Earth-Cum-Rock-Fill (ECRF) dam construction area, G Hill and G Dash Hill, among other locations. Vohra examined the quality of construction materials, including soil, sand, stone, aggregates and concrete. He witnessed quality tests conducted at the site and expressed satisfaction with the materials and the progress of works.
The CEO stressed that construction quality must not be compromised under any circumstances. He directed the project authorities and the executing agency to conduct quality tests regularly and maintain proper records. He also called for adequate precautions to prevent damage to completed and ongoing works during cyclonic conditions. Vohra emphasised that the prescribed daily targets must be met while maintaining the required quality standards.
State Water Resources Department Engineer-in-Chief K. Narasimha Murthy and Polavaram Project Superintending Engineer P. Ramachandra Rao attended the inspection. Chief Engineer (Quality) Seshubabu, Superintending Engineer Narasimha Rao and Executive Engineers Balakrishna, Srinivas and Premchand also took part. MEIL Polavaram Project General Manager A. Gangadhar Kumar, Deputy General Managers Murali Pammi and Guttapati Shankaraiah, and other officials were present as well.