NDSA team inspects under-construction Polavaram project for first time

Polavaram: A National Dam Safety Authority (NDSA) team on Saturday inspected the under-construction Polavaram Irrigation Project for the first time. The visit aimed to assess safety measures and monitoring arrangements, following directions from the Union Ministry of Jal Shakti.

Southern Zone Director Giridhar and Deputy Director Hemaditya comprised the team. They inspected the spillway, Gap-1, Gap-2 and Earth-cum-Rock Fill (ECRF) dam sections.

The team also held a review meeting with Water Resources department officials to examine safety instrumentation, monitoring systems and construction progress. Officials briefed the visitors on the Polavaram project through a scale model and a PowerPoint presentation at the project meeting hall. Superintending Engineer P Ramachandra Rao explained the progress of various components, including completed works and the status of ongoing construction.

Officials said an advanced Supervisory Control and Data Acquisition (SCADA) system is being established. It will enable real-time monitoring of project structures through sensors and other equipment.

IIT Roorkee preparing Emergency Action Plan

IIT Roorkee is preparing the project’s Emergency Action Plan, which will be submitted to the NDSA, officials informed the team. According to officials, the team expressed satisfaction with the safety arrangements and monitoring systems explained during the visit.

The inspection assumes significance as the NDSA has so far largely focused its inspections on completed dams. The authority was constituted under the Dam Safety Act, 2021.