Hyderabad: Deputy Chief Minister and Energy Minister Mallu Bhatti Vikramarka urged the Centre to clear Telangana’s power DPRs within 60 days. The Detailed Project Reports (DPRs) covered projects worth ₹25,096 crore under the Revamped Distribution Sector Scheme (RDSS).
Bhatti Vikramarka raised the demand at the Conference of State Power Ministers in New Delhi on Friday. Union Minister for Power, Housing and Urban Affairs Manohar Lal chaired the conference.
The Deputy Chief Minister sought the Centre’s full support to strengthen Telangana’s electricity generation, transmission and distribution infrastructure. He highlighted the need to expand infrastructure in line with the State’s rapidly growing electricity demand.
Furthermore, Bhatti Vikramarka outlined the government’s priorities for improving the power sector. These included accelerating smart meter installations, reducing distribution losses and solarising agricultural feeders.
He also stressed the need to clear pending government electricity dues and expand energy storage capacity. However, he said these initiatives required timely financial and policy support from the Union government.
Telangana’s power DPRs await clearance under RDSS
Bhatti Vikramarka said Telangana had submitted project proposals worth ₹25,096 crore to the Power Finance Corporation (PFC) on May 27. The proposals covered smart metering, distribution loss reduction and modernisation of the electricity distribution network under RDSS.
However, Telangana had received only ₹72 crore in budgetary support under the scheme so far. Meanwhile, the Deputy Chief Minister highlighted the steady improvement in the billing efficiency of Telangana’s power distribution companies. He said the companies had recorded consistent improvements over the past three years.
Against this backdrop, Bhatti Vikramarka sought clearance for Telangana’s power DPRs within 60 days. Additionally, he urged the Centre to extend the deadline for implementing RDSS works until March 31, 2028.