Hyderabad: The Hyderabad Metropolitan Water Supply and Sewerage Board (HMWSSB) is finalising arrangements to provide an additional Godavari water supply of 40 million gallons per day (MGD) to the city.
The new supply will serve as an alternative to water drawn from Singur and Manjeera sources, where officials anticipate possible shortages. The Water Board plans to divert water from Mallannasagar to the Ghanpur Master Balancing Reservoir (MBR) through a 1,600-mm pipeline.
Officials have targeted November 21 for completing the pipeline connection. Trial runs will begin after the work is completed. The proposed arrangement aims to strengthen Hyderabad’s drinking water supply by reducing dependence on Singur and Manjeera sources.
Officials said El Nino conditions could affect water availability in these sources. Consequently, the Water Board has accelerated arrangements to bring additional Godavari water into the existing supply network.
The 40 MGD supply is expected to address nearly 50 per cent of the anticipated drinking water deficit in areas dependent on Singur and Manjeera. The project will use water from Mallannasagar and transfer it to the Ghanpur MBR. From there, the additional supply will support Hyderabad’s drinking water requirements.
Mission Bhagiratha and HMWSSB networks to be connected
The project involves connecting the Mission Bhagiratha network with the Hyderabad Water Board’s infrastructure. A 1,600-mm-diameter pipeline will carry water from Mallannasagar towards the Ghanpur Master Balancing Reservoir.
The connection will allow the Water Board to receive additional Godavari water through the linked networks. Officials said the pipeline junction works at Ghanpur MBR had already been completed.
However, some remaining pipeline works were still underway as of Friday. The authorities planned to complete the connection by November 21 before initiating trial operations.
Hard rock formations delayed pipeline construction
The project encountered construction difficulties along a 150-metre stretch passing through a forest area. Officials said hard rock formations had slowed pipeline installation in this section.
As a result, the work took longer than originally planned. Despite the delay, the Water Board continued efforts to complete the remaining connection work. The authorities indicated that preparations were in their final stages.
HMWSSB Managing Director Ashok Reddy inspected the pipeline works on Friday, November 20. Mission Bhagiratha Engineer-in-Chief Kripakar Reddy accompanied him during the inspection.
The officials reviewed progress on the connection between the two water supply networks. They also examined the remaining work required before trial operations could begin.
During the visit, Ashok Reddy and Kripakar Reddy directed the engineering teams to expedite pending tasks. The inspection focused on completing the pipeline connection and preparing the system for trial runs.
Trial runs planned after November 21 connection deadline
The Water Board expects to begin trial runs after completing the pipeline connection. These trials will follow the final integration of the Mission Bhagiratha and HMWSSB networks.
The additional Godavari water supply will provide an alternative source for areas currently dependent on Singur and Manjeera. Officials expect the proposed 40 MGD diversion to meet nearly half of the projected drinking water shortfall in those areas.
However, the Water Board has not announced a specific date for beginning regular supply to consumers. The immediate priority remains completing the pipeline connection and starting trial operations.